The Saint heads toward 44 storeys next week.
Saturday Work
A crew will be on site this Saturday, February 3, doing a variety of tasks.
Current Construction Status
- Concrete work on Level 43 is complete.
- The Curtain Wall installation is complete to Level 26.
- Window Wall installation is complete to Level 22.
- The elevator components for the main interior elevators have been delivered.
This week’s construction outlook, Feb 5 – 9:
- Concrete pouring for the Level 44 slab floor will be the focus of the week, with completion expected by Friday.
- Curtain Wall window installation continues on Level 27
- Window Wall window installation continues on Level 23.
- Corridor stud installation will be active on Level 22.
- Interior suite stud installation will be active on Level 12.
- Drywall is active on Level 6.
Looking Ahead:
- The Hoist (external construction elevator) will be raised later this month.
Deliveries the week of February 5th to 9th:
- We expect up to three (3) Concrete deliveries this week.
- We expect two (2) Steel (rebar) deliveries this week.
- We expect one (1) or two (2) drywall deliveries this week.
- We expect two (2) window deliveries this week.
- There may also be one (1) carpentry delivery this week.
- There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
February Construction Liaison Meeting
We have scheduled the next meeting for Thursday, February 22 at 3 pm. A ZOOM Link for the meeting will be sent to those on our list prior to the meeting.
If you have not been a regular attendee but are interested in attending please send us an email at contact@thesaintconstruction.info for a link to the meeting.