March 15 Construction Update for the Saint

March 15 Construction Update for the Saint

Preparation work for Level 48 continues through the week of March 18.  Saturday Work Crews will be on site Saturday, March 16, doing a variety of tasks to set up next week’s work plan. Current Construction  Status  Concrete work has been completed for Level 47....
March 1 Construction Update for the Saint

March 1 Construction Update for the Saint

Crews will completing Level 47 the week of March 4.  Saturday Work Crews will be on site Saturday, March 2, doing a variety of tasks to set up next week’s work plan. Current Construction  Status  Concrete work is partially complete on Level 47. The last...