Work on Level 48 is set to be completed next week. 

March Construction Liaison Meeting

We have scheduled the next meeting for this coming Thursday, March 28 at 3 pm.

Subsequent meetings will be held on these dates:

  • Apr 25, 2024 03:00 PM
  • May 23, 2024 03:00 PM
  • Jun 27, 2024 03:00 PM

A ZOOM Link for the meeting will be sent to those on our list prior to the meeting, during the week of March 25th.

Saturday Work

Crews will be on site Saturday, March 23, doing a variety of tasks to set up next week’s work plan.

Current Construction  Status 

  • Concrete work has been completed for Level 47.
  • The Curtain Wall installation is complete to Level 33. 
  • Window Wall installation is complete to Level 29. 

  • NOTE: Toronto Hydro’s work to switch the Saint power supply to its permanent setup is now underway. The main power line is already on site, so Minto does not expect there to be work that will have an impact on the street (closures or interruptions), however, the work is entirely under the control and management of Toronto Hydro. 

This week’s construction outlook, March 25 – 29:

  • Work to complete Level 48.
  • Curtain Wall window installation continues on Level 34
  • Window Wall window installation continues on Level 30.
  • Corridor stud installation will be active on Level 26.
  • Interior suite stud installation will be active on Level 17.
  • Drywall and carpentry work is active on lower floors of the building, below Level 20.
  • Kitchen Installation is underway on the lower floors of the building. this coming week. Material deliveries for the kitchens will also get underway this coming week.

Deliveries the week of March 25 – 29:

There will be no concrete deliveries this week.

  • We expect two (2) Steel (rebar) deliveries this week.
  • We expect two (2) drywall deliveries this week.
  • We expect two (2) window deliveries this week.
  • We expect at one (1) carpentry & one (1) tile delivery this week. 
  • We expect at one (1) kitchen material delivery this week. 
  • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

Crane Light Update

A new timer has been installed on the crane light. However, last weekend it was inadvertently switched to manual mode by a new crew of subcontractors. The manual option will be eliminated to hopefully avoid this problem.

The crane light turns on at the start of construction hours and is set to turn off no later than 9 pm. 

If concrete finishing is necessary past 9 pm, crews may keep the crane light on in order to work safely, and the automatic turn off time will be adjusted as required.