Work on Level 49 is ongoing through the week.

UPDATED – Upcoming Construction Liaison Meetings

  • May 2, 2024 03:00 PM
  • May 30, 2024 03:00 PM
  • Jun 27, 2024 03:00 PM

Link for the meeting are be sent to those on our list prior to the meeting.

Saturday Work

Crews will be on site Saturday, April 6 doing a variety of tasks to set up the following week’s work plan.

Current Construction  Status 

  • Concrete work has been completed for Level 48.
  • The Curtain Wall installation is complete to Level 33. 
  • Window Wall installation is complete to Level 31. 

    This week’s construction outlook, April 8 – 12:

    • Work begins on Level 49.
    • The Hoist (external construction elevator) is set to be raised this week.
    • Curtain Wall window installation continues on Level 34
    • Window Wall window installation continues on Level 32.
    • Corridor stud installation will be active on Level 27.
    • Interior suite stud installation will be active on Level 17.
    • Drywall and carpentry work is active on lower floors of the building, below Level 20.
    • Tile on Level 4, Kitchens on Level 4, Countertops on Level 3.

    Deliveries the week of April 8 – 12:

    • Concrete deliveries
      • 3 to 4, per week, smaller amounts.
    • Other deliveries:
      • 2 Rebar (steel) deliveries.
      • 2 drywall deliveries.
      • 1 kitchen delivery.
      • 2 window deliveries.
      • 1 carpentry delivery. 
      • 1 tile delivery.
      • 1 countertop delivery.
    • NOTE:
      • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

        Crane Light Update

        A new timer has been installed on the crane light. However, last weekend it was inadvertently switched to manual mode by a new crew of subcontractors. The manual option will be eliminated to hopefully avoid this problem.

        The crane light turns on at the start of construction hours and is set to turn off no later than 9 pm. 

        If concrete finishing is necessary past 9 pm, crews may keep the crane light on in order to work safely, and the automatic turn off time will be adjusted as required.