Work on Level 49 continues this week.

Current Construction  Status 

  • Concrete work has been completed for Level 48.
  • The Curtain Wall installation is complete to Level 35. 
  • Window Wall installation is complete to Level 33. 
  • The Hoist (external construction elevator) has been raised. 
NOTE: Toronto Hydro’s work to connect the site to the permanent power supply has been completed. 

This week’s construction outlook, April 15 – 19:

  • Work continues on Level 49.
  • Curtain wall on level 36, and window wall on 34
  • The Hoist (external construction elevator) is being raised again this week.
  • Corridor studs are being installed on Level 27, and Sute studs are being installed on Level 17
  • Tile i sbeing installed on Level 5, Kitchens on Level 5, and Countertops on Level 4.
  • Drywall and carpentry work is ongoing through the building. 

      Deliveries the week of April 15 – 19:

      • 2 rebar (steel) deliveries.
      • Concrete deliveries at 3-4 per week, for small concrete pours on Level 49.
      • 2 drywall deliveries.
      • 1 kitchen deliveries.
      • 2 window deliveries.
      • 1 carpentry deliveries.
      • 1 tile deliveries.
      • 1 countertop deliveries.
      • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

            UPDATED – Upcoming Construction Liaison Meetings

            • May 2, 2024 03:00 PM
            • May 30, 2024 03:00 PM
            • Jun 27, 2024 03:00 PM

            Link for the meeting are be sent to those on our list prior to the meeting.

            Saturday Work

            Crews will be on site Saturday, April 20 doing a variety of tasks to set up the following week’s work plan.