Work on Level 49 will continue through April 26. 

Saturday Work

  • Crews will be on site Saturday, April 20 doing a variety of tasks to set up the following week’s work plan.
  • Current Construction  Status 

    • Concrete work has been completed for Level 48.
    • The Curtain Wall installation is complete to Level 39. 
    • Window Wall installation is complete to Level 34.
    • NOTE: Toronto Hydro’s work to connect the site to the permanent power supply has been completed. 

    This week’s construction outlook, April 22 – 26:

    • Work continues on Level 49.
    • Curtain wall on level 40, and window wall on 35.
    • The Hoist (external construction elevator) is being raised again this week.
    • Corridor studs are being installed on Level 27, and Sute studs are being installed on Level 17.
    • Tile is being installed on Level 6, Kitchens on Level 6, Countertops on Level 5.
    • Drywall and carpentry work is ongoing through the building. 

      Deliveries the week of April 22 – 26:

      • 2 rebar (steel) deliveries.
      • Concrete deliveries at 2-3 per week, for small concrete pours on Level 49.
      • 2 drywall deliveries.
      • 1 kitchen delivery.
      • 2 window deliveries.
      • 1 carpentry deliveries.
      • 1 tile delivery.
      • 1 countertop delivery.
      • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

            UPDATED – Upcoming Construction Liaison Meetings

            • May 2, 2024 03:00 PM
            • May 30, 2024 03:00 PM
            • Jun 27, 2024 03:00 PM

            Link for the meeting are be sent to those on our list prior to the meeting.