Work on Level 49 will continue through May 4. 

  • UPDATED – Construction Liaison Meeting – Thursday, May 2 at 3 pm. 

Saturday Work:

  • Once again, work crews will be on site Saturday, April 27 doing a variety of tasks to set up the following week’s work plan.

Current Construction  Status 

    • Concrete work has been completed for Level 48.
    • Curtain Wall installation is complete to Level 41. 
    • Window Wall installation is complete to Level 39.
    • Corridor studs complete to Level 28.
    • Suite studs complete to Level 20.
    • Tile complete to Level 8.
    • Kitchens complete to Level 6.
    • Countertops complete to Level 5.

    This week’s construction outlook, April 29 – May 3:

    • Work continues on Level 49.
    • Curtain wall on level 42, and window wall on 40.
    • The Hoist (external construction elevator) is being raised again this week.
    • Corridor studs are being installed on Level 31, and Sute studs are being installed on Level 21.
    • Tile is being installed on Level 9, Kitchens on Level 7, Countertops on Level 6.
    • Drywall and carpentry work is ongoing through the building. 

      Deliveries the week of April 29 – May 3:

      • 2 rebar (steel) deliveries.
      • Concrete deliveries at 2-3 per week, for small concrete pours on Level 49.
      • 2 drywall deliveries.
      • 1 kitchen delivery.
      • 2 window deliveries.
      • 1 carpentry deliveries.
      • 1 tile delivery.
      • 1 countertop delivery.
      • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

      UPDATED – Upcoming Construction Liaison Meetings

      • May 2, 2024 03:00 PM
      • May 30, 2024 03:00 PM
      • Jun 27, 2024 03:00 PM

      Link for the meeting are be sent to those on our list prior to the meeting.