May 10 Construction Update for the Saint

May 10 Construction Update for the Saint

Elevator component deliveries will continue through May 17.  Saturday Work: Once again, work crews will be on site Saturday, May 11, doing a variety of tasks to set up the following week’s work plan. This week’s construction outlook, May 13 – May 17:...
Construction Update for the Saint, May 3, 2024

Construction Update for the Saint, May 3, 2024

Work on Level 49 is now complete.  Saturday Work: Once again, work crews will be on site Saturday, May 4, doing a variety of tasks to set up the following week’s work plan. Current Construction  Status  Concrete work has been completed for Level 49. Curtain Wall...