Elevator component deliveries will continue through May 17.
Saturday Work:
- Once again, work crews will be on site Saturday, May 11, doing a variety of tasks to set up the following week’s work plan.
This week’s construction outlook, May 13 – May 17:
- Concrete work is underway for the roof level of Floor 49.
- Curtain wall installation is active on Level 44.
- Window wall installation is active on Level 40.
- Corridor studs are being installed on Level 32.
- Suite studs are being installed on Level 21.
- Tile is being installed on Level 9
- Kitchens on Level 8
- Countertops on Level 7.
- Drywall and carpentry work is ongoing throughout the building.
Current Construction Status
- Concrete work has been completed for Level 49.
- Curtain Wall installation is complete to Level 43.
- Window Wall installation is complete to Level 40.
- Corridor studs complete to Level 32.
- Suite studs complete to Level 22.
- Tile complete to Level 9.
- Kitchens complete to Level 8.
- Countertops complete to Level 6.
- There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
Deliveries the week of May 13 – 17:
- Elevator component deliveries continue through the week.
- Note to accommodate these deliveries, the site access area in use on Lombard may have to temporarily be expanded to ensure safe unloading operations, traffic personnel will be on site to assist in the management of this, as may be required.
- Concrete deliveries at 1 -2 per week, for the roof work.
- 2 drywall deliveries.
- 1 kitchen delivery.
- 2 window deliveries.
- 1 carpentry deliveries.
- 1 tile delivery.
- 1 countertop delivery.
UPDATED – Upcoming Construction Liaison Meetings
- May 30, 2024 03:00 PM
- Jun 27, 2024 03:00 PM
Link for the meeting are be sent to those on our list prior to the meeting.