Concrete work on the roof is ongoing through the coming week. 

Saturday Work

  • Once again, work crews will be on site Saturday, June 1, doing a variety of tasks to set up the following week’s work plan.

    This week’s construction outlook, June 3 – 7:

    • Concrete work continues for the roof level.
    • Curtain wall on Level 46.
    • Window wall on 44
    • Corridor studs on Level 37.
    • Suite studs on Level 27.
    • Tile on Level 11.
    • Kitchens on Level 11.
    • Countertops on Level 10.
    • Drywall and carpentry work is ongoing throughout the building. 

    Current Construction  Status 

      • Concrete work has been completed for Level 49 – all levels other than the roof.
      • Curtain Wall installation is complete to Level 45. 
      • Window Wall installation is complete to Level 43.
      • Corridor studs complete to Level 36.
      • Suite studs complete to Level 26.
      • Tile complete to Level 10.
      • Kitchens complete to Level 10.
      • Countertops complete to Level 9.
      • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

      Deliveries the week of June 3 – 7:

       

      • Concrete deliveries 2 this week, for the roof work. 

      • 2 drywall deliveries.

      • 1 kitchen delivery.

      • 2 window deliveries.

      • 1 carpentry delivery.

      • 1 tile delivery.

      • 1 countertop delivery.

      NEW – Upcoming Construction Liaison Meetings

        _________________________________________
      • The next regualalry schdeuled meeting is set for, Thursday, Jun 27, 2024, at 3:00 PM

      The Link for the meeting will be sent to those on our list, two days prior to the meeting.