Work on the roof level continues through coming week. 

Saturday Work

  • Once again, work crews will be on site Saturday, June 8, doing a variety of tasks to set up the following week’s work plan.

    This week’s construction outlook, June 10 – June 14:

    • Concrete work continues for the roof level.
    • Curtain wall on Level 47.
    • Window wall on 46
    • Corridor studs on Level 38.
    • Suite studs on Level 29.
    • Tile on Level 12.
    • Kitchens on Level 12.
    • Countertops on Level 11.
    • Drywall and carpentry work is ongoing throughout the building. 

    __

    Deliveries the week of June 10 – 14:

    • Concrete deliveries 2 this week, for the roof work. 

    • 2 drywall deliveries.

    • 1 kitchen delivery.

    • 2 window deliveries.

    • 1 carpentry delivery.

    • 1 tile delivery.

    • 1 countertop delivery.

    Current Construction  Status 

      • Concrete work has been completed for Level 49 – all levels other than the roof.
      • Curtain Wall installation is complete to Level 46. 
      • Window Wall installation is complete to Level 45.
      • Corridor studs complete to Level 37.
      • Suite studs complete to Level 28.
      • Tile complete to Level 11.
      • Kitchens complete to Level 11.
      • Countertops complete to Level 10.
      • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

      Upcoming Construction Liaison Meetings

        _________________________________________

      The next regularly scheduled meeting is set for, Thursday, Jun 27, 2024, at 3:00 PM

      • The Link for the meeting will be sent to those on our list, two days prior to the meeting.

      __

      A July meeting will be discussed at the meeting of June 27th. If it is agreed to porceed with a July meeting, it would be held on Thursday, July 27.