Work on the roof level continues through coming week. 

Saturday Work

  • Once again, work crews will be on site Saturday, June 15, doing a variety of tasks to set up the following week’s work plan.

    This week’s construction outlook,
    June 17 – June 21:

      • Concrete work continues for the roof level.
      • Curtain wall on Level 47.
      • Window wall on 46
      • Corridor studs on Level 38.
      • Suite studs on Level 29.
      • Tile on Level 13.
      • Kitchens on Level 13.
      • Countertops on Level 11.
      • Drywall and carpentry work is ongoing throughout the building. 

      __

      Deliveries the week of June 17 – 21:

      • Concrete deliveries 2 this week, for the roof work. 

      • 2 drywall deliveries.

      • 1 kitchen delivery.

      • 2 window deliveries.

      • 1 carpentry delivery.

      • 1 tile delivery.

      • 1 countertop delivery.

      Current Construction  Status 

        • Concrete work has been completed for Level 49 – all levels other than the roof.
        • Curtain Wall installation is complete to Level 46. 
        • Window Wall installation is complete to Level 45.
        • Corridor studs complete to Level 37.
        • Suite studs complete to Level 28.
        • Tile complete to Level 12.
        • Kitchens complete to Level 12.
        • Countertops complete to Level 10.
        • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

        Upcoming Construction Liaison Meetings

          _________________________________________

        The next regularly scheduled meeting is set for, Thursday, Jun 27, 2024, at 3:00 PM

        • The Link for the meeting will be sent to those on our list, two days prior to the meeting.

        __

        A July meeting will be discussed at the meeting of June 27th. If it is agreed to porceed with a July meeting, it would be held on Thursday, July 25.