Work on the roof level is ongoing.
Saturday Work
- Once again, work crews will be on site Saturday, June 22, doing a variety of tasks to set up the following week’s work plan.
This week’s construction outlook,
June 24 – June 28:
-
Roof concrete work ongoing.
-
Curtain wall on level 48
-
Window wall on level 47
-
Suite studs on 29,
-
Tile on Level 15,
-
Kitchens on Level 14,
-
Countertops on Level 11
-
Drywall and carpentry ongoing
Deliveries the week of June 24 – 28:
-
Concrete deliveries 2 this week, for the roof work.
-
1 – 2 drywall deliveries for this week.
-
1 kitchen delivery.
-
2 window deliveries.
-
1 carpentry delivery.
-
1 tile delivery.
-
1 countertop delivery.
- There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
Upcoming Construction Liaison Meetings
- _________________________________________
The next regularly scheduled meeting is set for next week on Thursday, Jun 27, 2024, at 3:00 PM
- The Link for the meeting will be sent to those on our list, two days prior to the meeting.
- A July meeting will be discussed at the meeting of June 27th. If it is agreed to proceed with a July meeting, it would be held on Thursday, July 25.