Work is still proceeding on the roof level at the Saint.  

Saturday Work

  • Once again, work crews will be on site Saturday, July 13, doing a variety of tasks to set up the following week’s work plan

    Updates: 

    • The site now has access to its permanent power supply. 
    • The crane will remian in service on the site through July and August. 
    • Prep work for the installation of the incoming Bell and Rogers communication lines is underway and will continue through the coming week.  Minimal disruption is expected, however rolling scaffolding and overhead protection will be in use to ensure their work is conducted efficiently and safely. 

    This week’s construction outlook,
    July 15 – July 19:

      • Roof concrete work ongoing.

      • Curtain wall on level 48.

      • Window wall on level 47.

      • Suite studs on 29.

      • Tile on Level 17.

      • Kitchens on Level 16.

      • Countertops on Level 13.

      • Drywall and carpentry ongoing.

      Deliveries the week of July 15 – 19:

      • Concrete delivery, 1 this week to support the roof work. 

      • 2 drywall deliveries for this week.

      • 1 kitchen delivery.

      • 2 window deliveries.

      • 1 carpentry delivery.

      • 1 tile delivery.

      • 1 countertop delivery.

      _____________________________________________________________________________

      • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

      Upcoming Construction Liaison Meetings

        _________________________________________

      The next regularly scheduled meeting is set for next week on Thursday, July 25, 2024, at 3:00 PM

      • The Link for the meeting will be sent to those on our list, two days prior to the meeting.
      • An August meeting will be discussed at the meeting of July 25th. If it is agreed to proceed with an August meeting, it would be held on Thursday, August 22nd.