Landscaping work has started along Church and Lombard. 

    Roof work continues through the coming week.

    Saturday Work – Civic Holiday 

      • Once again, work crews will be on site Saturday, August 3, doing a variety of tasks to set up the following week’s work plan
      • The Site will be closed on Monday August 5, for the Civic Holiday, with work resuming on Tuesday, August 6. 
      • NOTE: Work by Rogers to connect the site for Rogers phone and internet service has been completed. 

      This week’s construction outlook,
      August 6 – 9:

        • Landscaping work along Lombard Street and Church Street

          • The landscaping work does not include the area around the Hoist (external construction elevators), as it continues to operate.
        • Roof concrete work ongoing.

        • Curtain wall on level 49.

        • Window wall on level 47.

        • Suite studs on 32.

        • Tile on Level 18.

        • Kitchens on Level 17.

        • Countertops on Level 16.

        • Drywall and carpentry ongoing.

        Deliveries the week of August 6 – 9:

        • Concrete delivery, 1 this week to support the roof work. 

        • 2 drywall deliveries for this week.

        • 1 kitchen delivery.

        • 1 window delivery.

        • 1 carpentry delivery.

        • 1 tile delivery.

        • 1 countertop delivery

        • 1 appliance delivery.

        _____________________________________________________________________________

        • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

        Looking Ahead 

        • Bell work to connect the site to Bell Services is expected to begin later this month (August 2024). 
        • The crane is expected to be dismantled and removed in September. 
        • Move-ins to the Saint are expected to begin at the end of the year. 
        • The Hoist (external construction elevators) is expected to remain in place through 2024. 
        • Our next construction liaison meeting will be held on September 26, 2024. 

        Upcoming Construction Liaison Meetings

        At the July 25 construction liaison meeting it was decided to not hold a meeting August. If the need arises to hold a meeting then this may be revised, with due notice. 

          _________________________________________

        Accordingly, the next regularly scheduled meeting is set for next week on Thursday, September 26, 2024, at 3:00 PM

        • The Link for the meeting will be sent to those on our list, two days prior to the meeting.