Landscaping work has started along Church and Lombard.
Roof work continues through the coming week.
Saturday Work – Civic Holiday
- Once again, work crews will be on site Saturday, August 3, doing a variety of tasks to set up the following week’s work plan.
- The Site will be closed on Monday August 5, for the Civic Holiday, with work resuming on Tuesday, August 6.
- NOTE: Work by Rogers to connect the site for Rogers phone and internet service has been completed.
This week’s construction outlook,
August 6 – 9:
-
Landscaping work along Lombard Street and Church Street
-
The landscaping work does not include the area around the Hoist (external construction elevators), as it continues to operate.
-
-
Roof concrete work ongoing.
-
Curtain wall on level 49.
-
Window wall on level 47.
-
Suite studs on 32.
-
Tile on Level 18.
-
Kitchens on Level 17.
-
Countertops on Level 16.
-
Drywall and carpentry ongoing.
Deliveries the week of August 6 – 9:
-
Concrete delivery, 1 this week to support the roof work.
-
2 drywall deliveries for this week.
-
1 kitchen delivery.
-
1 window delivery.
-
1 carpentry delivery.
-
1 tile delivery.
-
1 countertop delivery
-
1 appliance delivery.
_____________________________________________________________________________
- There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
Looking Ahead
- Bell work to connect the site to Bell Services is expected to begin later this month (August 2024).
- The crane is expected to be dismantled and removed in September.
- Move-ins to the Saint are expected to begin at the end of the year.
- The Hoist (external construction elevators) is expected to remain in place through 2024.
- Our next construction liaison meeting will be held on September 26, 2024.
Upcoming Construction Liaison Meetings
At the July 25 construction liaison meeting it was decided to not hold a meeting August. If the need arises to hold a meeting then this may be revised, with due notice.
- _________________________________________
Accordingly, the next regularly scheduled meeting is set for next week on Thursday, September 26, 2024, at 3:00 PM
- The Link for the meeting will be sent to those on our list, two days prior to the meeting.