Landscaping work is ongoing along Church Street. 

    Saturday Work  

      • Once again, work crews will be on site Saturday, August 10, doing a variety of tasks to set up the following week’s work plan

        This week’s construction outlook,
        August 12 – 16:

          • Landscaping work along the Church Street frontage.

          • Roof concrete work ongoing.

          • Curtain wall on level 49.

          • Window wall on level 47.

          • Suite studs on 33.

          • Tile on Level 19.

          • Kitchens on Level 18.

          • Countertops on Level 16.

          • Drywall and carpentry ongoing.

          Deliveries the week of August 12 – 16:

          • Concrete delivery, 1 this week to support the roof work. 

          • 2 drywall deliveries for this week.

          • 1 kitchen delivery.

          • 1 window delivery.

          • 1 carpentry delivery.

          • 1 tile delivery.

          • 1 countertop delivery

          • 1 appliance delivery.

          _____________________________________________________________________________

          • There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

          Looking Ahead 

          • Rogers work to connect the site to Rogers Services is expected to begin later this month (August 2024). 
          • The crane is expected to be dismantled and removed in September. 
          • Move-ins to the Saint are expected to begin at the end of the year. 
          • The Hoist (external construction elevators) is expected to remain in place through 2024. 
          • Landscaping work on Lombard will follow work that is now underway on Church Street. Note that the landscaping work  does not include the area around the Hoist (external construction elevators), as it continues to operate. 
          • Our next construction liaison meeting will be held on September 26, 2024. 

          Upcoming Construction Liaison Meetings

          At the July 25 construction liaison meeting it was decided to not hold a meeting August. If the need arises to hold a meeting then this may be revised, with due notice. 

            _________________________________________

          Accordingly, the next regularly scheduled meeting is set for next week on Thursday, September 26, 2024, at 3:00 PM

          • The Link for the meeting will be sent to those on our list, two days prior to the meeting.