Roof work & Landscaping work on Church Street are ongoing. 

    Saturday Work  

      • Once again, work crews will be on site Saturday, September 7, doing a variety of tasks to set up the following week’s work plan

      This week’s construction outlook,
      September 9 – 13:

          • Landscaping work continues along the Church Street frontage.
          • At the ‘Top of house’ (roof) both the curtain wall and the window wall frames are getting closer to completion though work will continue through the coming week.
          • Suite Studs are active on Level 37.
          • Tile is active on Level 23.
          • Kitchens are active on Level 21.
          • Countertops on Level 19.
          • Drywall and carpentry ongoing.

        Deliveries the week of September 9 – 13:

         

          • Concrete delivery: 1 this week to support the roof work. 
          • We expect up to 2 drywall deliveries for this week.
          • We expect 1 kitchen delivery.
          • We expect 1 window delivery.
          • We expect 1 carpentry delivery.
          • We expect 1 tile delivery.
          • We expect 1 countertop delivery.
          • There may also be 1 appliance delivery.

        _____________________________________________________________________________

        There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

        Looking Ahead

        • Planned work by Rogers to connect the site to Rogers Services will commence mid-September.
        • The crane is expected to be dismantled and removed in September. 
        • Move-ins to the Saint are expected to begin at the end of the year. 
        • The Hoist (external construction elevators) is expected to remain in place through 2024. 
        • Landscaping work on Lombard will follow work that is now underway on Church Street. Note that the landscaping work  does not include the area around the Hoist (external construction elevators), as it continues to operate. 
        • Our next construction liaison meeting will be held on September 26, 2024. 

        Upcoming Construction Liaison Meetings

        At the Thursday, July 25 construction liaison meeting it was decided to not hold a meeting August. 

        The next regularly scheduled meeting is set for next week on Thursday, September 26, 2024, at 3:00 PM

        • The Zoom Link for the meeting will be sent to those on our list, two days prior to the meeting.