Roof work & Landscaping work on Church Street continue this week.
Report of noise this past Sunday, September 15
- We received reports of noise that appeared to be coming from the Saint construction site this past Sunday, September 15. Upon a thorough investigation, there were some workers on site conducting a scheduled and necessary power down on the Saint’s main power system. However, this does not cause any significant noise. We can only assume that any perceived construction noise was coming from another site in the neighbourhood.
This week’s construction outlook,
September 16 – 20:
-
- Landscaping work continues along the Church Street frontage.
- At the ‘Top of house’ (roof) both the curtain wall and the window wall frames are getting closer to completion though work will continue through the coming week.
- The Building Maintenance Unit is being installed.
- Derrick prep work will begin this week
- Suite Studs are active on Level 38.
- Tile is active on Level 24.
- Kitchens are active on Level 22.
- Countertops on Level 20.
- Drywall and carpentry ongoing.
- Rogers is expected to install their connections to the site this week and/or next week.
Saturday Work
- Once again, work crews will be on site Saturday, September 21, doing a variety of tasks to set up the following week’s work plan.
Deliveries the week of September 16 – 20:
-
- Concrete delivery: Possibly 1 this week to support the roof work.
- We expect up to 2 drywall deliveries for this week.
- We expect 1 kitchen delivery.
- We expect 1 window delivery.
- We expect 1 carpentry delivery.
- We expect 1 tile delivery.
- We expect 1 countertop delivery.
- There may also be 1 appliance delivery.
_____________________________________________________________________________
There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
Looking Ahead
- The crane is expected to be dismantled and removed by the end of September.
- Move-ins to the Saint are expected to begin at the end of the year.
- The Hoist (external construction elevators) is expected to remain in place through 2024.
- Landscaping work on Lombard will follow work that is now underway on Church Street. Note that the landscaping work does not include the area around the Hoist (external construction elevators), as it continues to operate.
- Our next construction liaison meeting will be held on September 26, 2024.
Upcoming Construction Liaison Meetings
At the Thursday, July 25 construction liaison meeting it was decided to not hold a meeting in August.
The next regularly scheduled meeting is set for next week on Thursday, September 26, 2024, at 3:00 PM
- The Zoom Link for the meeting will be sent to those on our list, two days prior to the meeting.