,This Week: Construction Liasion Meeting, Thursday.
At the site:
Derrick prep & Landscaping work ongoing. 

.

Construction Liasion Meeting

  • Our October construction liaison meeting will be held this Thursday, October 24, 2024, at 3 pm via ZOOM. 

Saturday Work

    • Crews are expected to be active on site on Saturday, October 26.  

    This week’s construction outlook,
    October 21 – 25:

        • Landscaping work continues along the Church Street frontage.
        • Roof work ongoing: 
        • The roof curtain wall frames nearing completion.
        • Building Maintenance Unit installation continues. 
        • Derrick prep work continues this week.
          • NOTE: Derricks will be used to take the crane down.
        • Suite Studs are active on Level 44.
        • Tile is active on Level 27.
        • Kitchens are active on Level 25.
        • Countertops on Level 23.
        • Drywall and carpentry ongoing.
        • Rogers work to connect the site is underway and expected to continue through the week of the 21st. 

      Deliveries the week of October 21 – 25:

       

        • Concrete deliveries 1 per week, small pours
        • 2 drywall
        • 1 kitchen
        • 1 window
        • 1 carpentry
        • 1 tile
        • 1 countertop
        • 1 appliance  

      _____________________________________________________________________________

      There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

      Looking Ahead

      • The Derrick which will be used in the process to lower the main crane may be delivered next week (the week of October 28th).
      • There is still not a confirmed date for the dismantling and removal of the main crane. However, it is still likely that this will occur in the first week of November.  
      • Move-ins to the Saint are expected to begin at the end of the year. 
      • The Hoist (external construction elevators) is expected to remain in place through 2024 and into January, 2025. 
      • Landscaping work on Lombard will follow work that is now underway on Church Street. Note that the landscaping work  does not include the area around the Hoist (external construction elevators), as it continues to operate. 
      • Our November construction liaison meeting will be held on Thursday, November 28, 2024, at 3 pm via ZOOM.