Crane Removal November 9 – 10
Landscape & Building Work November 11 – 15 

Saturday & Sunday Work

    This weekend the Crane Will Be Taken Down, November 9 – 10.

      • The crane is set to be taken down from Saturday November 9, at 7:00 am,through Sunday November 10, at 3:00 pm.
      • (Please Click Here for the Downloadable PDF Notice)
      • The image below illustrates the Lombard Street Closure that will be required to safely take the crane down on November 9 & 10.
      • Local residents will be able acceess their buildings, though there may unfortuantely be some necessary delays. 
      • Emergency Vehicles will have access as may be required. 

    This week’s construction outlook November 11 – 15:

    • Roof work ongoing.

      • Top of house (roof) curtain wall frames, and Building Maintenance Unit installation work ongoing through the week.
      • Large and Small Derrick Installation. 
    • Landscape Work is expected to be complted by the end of the week.
    • Suite studs on Level 46, Tile on Level 30, Kitchens on Level 28, Countertops on Level 26
    • Drywall and carpentry ongoing throughout the building. 

    Deliveries the week of November 11 – 15:

    • Concrete deliveries 1 per week, small pours
    • 2 drywall
    • 1 kitchen
    • 1 window
    • 1 carpentry
    • 1 tile
    • 1 countertop
    • 1 appliance  

      _____________________________________________________________________________

      There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

      Looking Ahead

      • Move-ins to the Saint are expected to begin at the end of the year. 
      • The Hoist (external construction elevators) is expected to remain in place through 2024 and into January, 2025. 
      • Our November construction liaison meeting will be held on Thursday, November 28, 2024, at 3 pm via ZOOM.