Small derrick installation in progress.
Streetscape work substantially complete.

Saturday  Work

      • There will be crews on site this Saturday November 16 doing a variety of prepartaion work for next week.
      • We also expect that there will be crews on site the following Saturday, November 23. 

    This week’s construction outlook November 18 – 22:

    ___

    • Roof work ongoing:

      • Top of house (roof) curtain wall frames, and Building Maintenance Unit installation work ongoing through the week.
      • Small Derrick Installation. 
      • Streetscape Work is substantially complete.
    • Interior work ongoing:

      • Suite studs on Level 46,
      • Tile on Level 30,
      • Kitchens on Level 29,
      • Countertops on Level 27
      • Drywall and carpentry ongoing throughout the building. 

    Deliveries the week of November 18 – 22:

    • Concrete deliveries 1 per week, small pours
    • 2 drywall
    • 1 kitchen
    • 1 window
    • 1 carpentry
    • 1 tile
    • 1 countertop
    • 1 appliance  

      _____________________________________________________________________________

      There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

      Looking Ahead

      • Move-ins to the Saint are expected to begin at the end of the year. 
      • The Hoist (external construction elevators) is expected to remain in place through 2024 and into January, 2025. 
      • Our November construction liaison meeting will be held on Thursday, November 28, 2024, at 3 pm via ZOOM.