Focus on interior work for the week of December 2.

Updates & Saturday Work

  • Small & mini derricks were in the process of being removed on Friday, November 29.
  • The first set of unit inspections are underway.
  • Streetscape work is substantially complete. 
  • There will be crews on site Saturday, November 30. 

This week’s construction outlook December 2 – 6:

___

  • Roof work ongoing:

    • Top of house (roof) curtain wall frames, and Building Maintenance Unit installation work ongoing through the week.
    • Interior work ongoing:

      • Suite studs on Level 47,
      • Tile on Level 31,
      • Kitchens on Level 20,
      • Countertops on Level 28
      • Drywall and carpentry ongoing throughout the building. 

    Deliveries the week of Decemebr 2 – 6:

    • Concrete deliveries 1 per week, small pours

    • 2 drywall

    • 1 kitchen

    • 1 window

    • 1 carpentry

    • 1 tile

    • 1 countertop

    • 1 appliance  

      _____________________________________________________________________________

      There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.

      Looking Ahead

      • Move-ins to the Saint are set to begin in December.  
      • The Hoist (external construction elevators) is expected to remain in place through 2024 and into early January, 2025. 
      • Tree planting will occur in the new year when the weather is warm enough.