Focus on interior work for the week of December 2.
Updates & Saturday Work
- Small & mini derricks were in the process of being removed on Friday, November 29.
- The first set of unit inspections are underway.
- Streetscape work is substantially complete.
- There will be crews on site Saturday, November 30.
This week’s construction outlook December 2 – 6:
___
-
Roof work ongoing:
- Top of house (roof) curtain wall frames, and Building Maintenance Unit installation work ongoing through the week.
-
Interior work ongoing:
- Suite studs on Level 47,
- Tile on Level 31,
- Kitchens on Level 20,
- Countertops on Level 28
- Drywall and carpentry ongoing throughout the building.
Deliveries the week of Decemebr 2 – 6:
-
Concrete deliveries 1 per week, small pours
-
2 drywall
-
1 kitchen
-
1 window
-
1 carpentry
-
1 tile
-
1 countertop
-
1 appliance
-
_____________________________________________________________________________
There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
Looking Ahead
- Move-ins to the Saint are set to begin in December.
- The Hoist (external construction elevators) is expected to remain in place through 2024 and into early January, 2025.
- Tree planting will occur in the new year when the weather is warm enough.