Focus on roof & interior work for the week of December 9.
Updates & Saturday Work
- Small & mini derricks have been removed
- The first set of unit inspections are underway.
- Streetscape work is substantially complete.
- There will be crews on site Saturday, December 7.
This week’s construction outlook December 9 – 13:
___
-
Minor Roof work ongoing:
- Top of house (roof) curtain wall frames and related work through the week.
-
Interior work ongoing:
- Suite studs on Level 46,
- Tile on Level 30,
- Kitchens on Level 29,
- Countertops on Level 27
- Drywall and carpentry ongoing throughout the building.
Deliveries the week of December 9 – 13:
-
Concrete deliveries 1 per week, small pours
-
2 drywall
-
1 kitchen
-
1 window
-
1 carpentry
-
1 tile
-
1 countertop
-
1 appliance
-
_____________________________________________________________________________
There will be (3) Traffic Management staff and one (1) Paid Duty Police Officer will be on site to manage traffic flows this coming week.
Looking Ahead
- Move-ins to the Saint are set to begin in December.
- The Hoist (external construction elevators) is expected to remain in place through 2024 and into early January, 2025.
- Tree planting will occur in the new year when the weather is warm enough.