Construction Update for the Saint.

Construction Update for the Saint.

4th floor work remains the focus at The Saint.   Work at the Saint remains focused on the 4th floor, placing rebar (steel) into the forming structure, and then pouring Level 4 in sections. After each section is poured it will be finished to ensure it is level, smooth...
The Saint, September 6 – 9, 2022

The Saint, September 6 – 9, 2022

Work on the 4th Level of the Saint progresses this week. Construction highlights: Vertical columns and walls are being formed and poured. Concrete slab work is ongoing in stages and sections: forming, rebar installation, concrete pouring and finishing. Deliveries will...