March 1 Construction Update for the Saint

March 1 Construction Update for the Saint

Crews will completing Level 47 the week of March 4.  Saturday Work Crews will be on site Saturday, March 2, doing a variety of tasks to set up next week’s work plan. Current Construction  Status  Concrete work is partially complete on Level 47. The last...
February 23 Construction Update for the Saint

February 23 Construction Update for the Saint

Crews will be pouring concrete for Level 47 starting this coming week.  Saturday Work As all the work to move the outrigger platform was successfully completed last Saturday, there will only be normal preparation and general housekeeping work this Saturday, February...
The Saint – February 9, 2024, Update

The Saint – February 9, 2024, Update

The Saint will begin work on the 45th storey next week.  Saturday Work A crew will be on site this Saturday, February 10, doing a variety of tasks.   Current Construction  Status  Concrete work on Level 44 is substantially complete today. The Curtain Wall...