by admin | Sep 22, 2023 | Construction Updates
Level 28 concrete work set to begin this coming week. Saturday Work: There will be a crew on this Saturday, September 23, carrying out a variety of tasks. Outlook for September 25 – 29: Crews will begin rebar, forming, concrete pouring & finishing for Level...
by admin | Sep 15, 2023 | Construction Updates
Level 27 to be completed early next week. Saturday Work: There will be a crew on this Saturday, September 16, carrying out a variety of tasks. Outlook for September 18 – 22: Crews will work to complete the concrete pouring & finishing for Level 27 this...
by admin | Sep 8, 2023 | Construction Updates
26th Floor Concrete Pouring set to be completed by September 15. Saturday Work: There will be a crew on this Saturday, September 9, carrying out a variety of tasks. Outlook for the week of September 11 – 15: Crews will working to complete the concrete pouring...
by admin | Sep 1, 2023 | Construction Updates
Concrete Pouring on the 26th Floor September 5th – 8th. Saturday Work: There will be a crew on this Saturday, September 2, carrying out a variety of tasks. Site Closed – Labour Day, Monday, September 4th Outlook for the week of September 5 – 8:...
by admin | Aug 31, 2023 | Construction Updates
Crane Lights at the Saint. Please Note: Our regular construction update will be posted on Friday September 1, 2023. Crane Lights: Unfortunately the concrete finishing crew left on the overhead light from the crane at The Saint. Minto’s construcion...
by admin | Aug 25, 2023 | Construction Updates
The Saint: work will begin on the 26th Floor next week. Saturday Work: There will be a crew on this Saturday, August 26, carrying out a variety of tasks. Outlook for the week of August 28 – September 1: Crews will begin forming, installing rebar, pouring...