by admin | Nov 3, 2023 | Construction Updates
Work to reach Level 34 the week of November 6th. Saturday Work: There will be work on-site this Saturday, November 4. Outlook for the week November 6th: Crews will aim to complete Level 34 this week. Concrete finishing may go late on colder days, given the impact...
by admin | Nov 1, 2023 | Construction Updates
An update on crane lights & concrete finishing. Crane Lights Following recent concerns regarding the crane lights, Minto has had the construction team check the settings and positioning of the lights. After the review, all the lights on east, south, and west are...
by admin | Oct 27, 2023 | Construction Updates
Aiming to complete Level 33 by November 3rd. Saturday Work: There will be work on-site this Saturday, October 28. Outlook for October 30 – November 3: Crews will aim to complete Level 33 this week. Window installation is now active on Level 22. Interior work:...
by admin | Oct 20, 2023 | Construction Updates
Work on the 31st level continues into the week of the 23rd. Saturday Work: There will be work on-site this Saturday, October 21. Outlook for October 23 – 27: Crews will aim to complete Level 31 this week. Window installation is now active on Level 22. Interior...
by admin | Oct 13, 2023 | Construction Updates
Saturday work as the Saint aims to reach 31 storeys. Saturday Work: There will be work on-site this Saturday, October 14. Outlook for October 16 – 20: Crews will aim to complete Level 31 this week. Window installation is now active on Level 20. Interior work:...
by admin | Oct 6, 2023 | Construction Updates
The Site will be closed on Monday October 9th for Thanksgiving. Saturday Work: There will be some minor work this Saturday, October 7. Outlook for October 10 – 13: Crews will aim to complete Level 30 this week. Window installation is now active on Level 19....