by admin | Feb 9, 2024 | Construction Updates
The Saint will begin work on the 45th storey next week. Saturday Work A crew will be on site this Saturday, February 10, doing a variety of tasks. Current Construction Status Concrete work on Level 44 is substantially complete today. The Curtain Wall...
by admin | Feb 2, 2024 | Construction Updates
The Saint heads toward 44 storeys next week. Saturday Work A crew will be on site this Saturday, February 3, doing a variety of tasks. Current Construction Status Concrete work on Level 43 is complete. The Curtain Wall installation is complete to Level 26. ...
by admin | Jan 29, 2024 | Construction Updates
The Saint heads to 43 storeys this week. Saturday Work A crew will be on site this Saturday, February 3, doing a variety of tasks. Current Construction Status Concrete work on Level 42 is complete. The Curtain Wall installation has reached the 26th floor. ...
by admin | Jan 26, 2024 | Construction Updates
Friday Update for the Saint: NOTE: As many may have noticed, earlier today, a concrete form blew out from the Madison construction site on the west side of Church Street at Lombard. Streetcars were halted, and the entire street was closed from Adelaide to Richmond...
by admin | Jan 22, 2024 | Construction Updates
Construction Liaison Meeting this Thursday, January 25, at 3 pm. Saturday Work A crew will be on site this Saturday, January 27 doing a variety of tasks. Current Construction Status Concrete work on Level 41 is complete. The Curtain Wall installation has...
by admin | Jan 15, 2024 | Construction Updates
Construction Liaison Meeting RESCHEDULED to January 25, 3 pm. Saturday Work A crew will be on site this Saturday, January 20 doing a variety of tasks. Current Construction Status Concrete work on Level 40 is substantially complete. Curtain Wall installation...