Construction Update for June 4, 2021

Construction Update for June 4, 2021

Excavation has reached the P6 Level at The Saint.  This week has seen a key milestone reached excavation work has reached the final underground level — P6 — of what will be the underground parking floors of the Saint. There will be no work on site...
Construction update for the Saint, May 31, 2021

Construction update for the Saint, May 31, 2021

Excavation work to continue through the week of May 31.  This will be another week focussed on rilling, excavating and hauling away soil off-site. We do not expect any major deliveries this week. As we noted in our last update, later in June the site will see a new...
Construction Update for the Saint, May 13, 2021

Construction Update for the Saint, May 13, 2021

Long Reach Excavator arriving on site on Saturday, May 15. Excavation work is continuing on site. Work is pressing on below the P4 level but as the soil composition is different at this level progress is steady but slower. This Saturday, May 15, a long reach excavator...