The Saint – February 9, 2024, Update

The Saint – February 9, 2024, Update

The Saint will begin work on the 45th storey next week.  Saturday Work A crew will be on site this Saturday, February 10, doing a variety of tasks.   Current Construction  Status  Concrete work on Level 44 is substantially complete today. The Curtain Wall...
January 29th Construction Update for the Saint.

January 29th Construction Update for the Saint.

The Saint heads to 43 storeys this week.  Saturday Work A crew will be on site this Saturday, February 3, doing a variety of tasks.   Current Construction  Status  Concrete work on Level 42 is complete. The Curtain Wall installation has reached the 26th floor. ...
Friday Update for the Saint, January 26, 2024

Friday Update for the Saint, January 26, 2024

Friday Update for the Saint:    NOTE: As many may have noticed, earlier today, a concrete form blew out from the Madison construction site on the west side of Church Street at Lombard. Streetcars were halted, and the entire street was closed from Adelaide to Richmond...
January 15th Construction Update for the Saint.

January 15th Construction Update for the Saint.

Construction Liaison Meeting RESCHEDULED to January 25, 3 pm.   Saturday Work A crew will be on site this Saturday, January 20 doing a variety of tasks.   Current Construction  Status  Concrete work on Level 40 is substantially complete. Curtain Wall installation...