Construction InformationThe April Construction Summary Report is now available.Site work for the coming week, May 16 - 20 Both the Carpenters’ Union and LIUNA, the Laborers’ International Union, remain on strike this week. There is also the  prospect of additional...

Strikes slow work this week at the Saint construction site.

Strikes slow work this week at the Saint construction site.

Impact of the LIUNA & Carpenters Union job actions continue. Week of May 9, 2022 LIUNA, the Laborers’ International Union, remains on strike this week. LIUNA covers workers who do high-rise forming, self-levelling forming, tile, railing, carpet, and hardwood...

Mid Week Update: Labour action slows work at the Saint.

Mid Week Update: Labour action slows work at the Saint.

Impact of the LIUNA job action felt at the Saint. Mid-Week Update LIUNA, the Laborers’ International Union, is currently pursuing a job action. This means that the formworkers and crane operators are effectively on strike. Construction management at the Saint are not...

Construction Outlook for the Week of May 2, 2022

Construction Outlook for the Week of May 2, 2022

Concrete work and rebar work continue at the Saint. Outlook for the week of May 2, 2022 Work will remain focussed on forming and pouring vertical walls and columns this week. Once the verticals are completed work will begin on forming, installing stell rebar and then...

Mid-Week Construction Update for the Saint

Mid-Week Construction Update for the Saint

Constrtuction Liaison Meeting this Thursday. Mid-Week Update This week concrete work is ongoing with regular deliveries at the site gate that is now up on Lombard Street. Work on installing the hoardings and overhead protection on Lombard is continuing over the coming...

Construction Outlook for the Saint, April 18 – 22, 2022

Construction Outlook for the Saint, April 18 – 22, 2022

Hoarding installation set to get underway this week.The overall outlook for the week of April 18th: This week concrete work will be focussed on the vertical columns and walls, which includes, forming, placing steel (rebar), pouring the columns. We expect this work...

March Report. April Construction Liaison Mtg.

March Report. April Construction Liaison Mtg.

  Our March Construction Summary Report is available as downloadable PDF by clicking on this link. Our April Construction Liaison Meeting will be held via ZOOM on Thursday, April 28 at the 3 pm. If you are a local resident or businessperson and wish to attend...

Work at the Saint April 9 – April 15, 2022

Work at the Saint April 9 – April 15, 2022

Saturday Work April 9. Outlook for the week of April 11th.  Saturday, April 9th: There will be a crew on site this Saturday conducting a variety of tasks mostly focused on preparing for next week's work goals.  Steel and concrete deliveries this coming week: There...

Construction Outlook for the Week of April 4, 2022

Construction Outlook for the Week of April 4, 2022

Steel Deliveries and Concrete Work set for the week of April 4.  Work in progress at the Saint. Despite recent delivery challenges with the concrete supply, work has continued on the ground floor slab. The forming and pouring of vertical columns rising from the ground...

Upcomming Events

July

21

Community Information Session

Please join us on Tuesday, July 21 at 6:30 pm for an online information session reviewing the initial phases of construction of Minto’s The Saint at 89 Church Street.

Please click here for the details of the information session. 