Construction Liaison Mtg September 28 – Construction Update.
Level 28 concrete work set to begin this coming week. Saturday Work: There will be a crew on this Saturday, September 23, carrying out a variety of tasks. Outlook for September 25 - 29: Crews will begin rebar, forming, concrete pouring & finishing for Level 28...
September 15 Construction Update: Next Construction Liaison Mtg.
Level 27 to be completed early next week. Saturday Work: There will be a crew on this Saturday, September 16, carrying out a variety of tasks. Outlook for September 18 - 22: Crews will work to complete the concrete pouring & finishing for Level 27 this week....
September 8 Construction Update for the Saint
26th Floor Concrete Pouring set to be completed by September 15. Saturday Work: There will be a crew on this Saturday, September 9, carrying out a variety of tasks. Outlook for the week of September 11 - 15: Crews will working to complete the concrete pouring &...
September 1st Construction Update for the Saint
Concrete Pouring on the 26th Floor September 5th - 8th. Saturday Work: There will be a crew on this Saturday, September 2, carrying out a variety of tasks. Site Closed - Labour Day, Monday, September 4th Outlook for the week of September 5 - 8: Crews will be pouring...
Crane Lights at the Saint
Crane Lights at the Saint. Please Note: Our regular construction update will be posted on Friday September 1, 2023. Crane Lights: Unfortunately the concrete finishing crew left on the overhead light from the crane at The Saint. Minto's construcion management...
August 25 Construction Update for the Saint.
The Saint: work will begin on the 26th Floor next week. Saturday Work: There will be a crew on this Saturday, August 26, carrying out a variety of tasks. Outlook for the week of August 28 - September 1: Crews will begin forming, installing rebar, pouring &...
August 18 Construction Update for the Saint.
The Saint: work set to begin for the 25th Floor next week. Saturday Work: There will be a crew on this Saturday, August 19, carrying out a variety of tasks. Outlook for the week of August 21 - August 26: Crews will be pouring concrete for level 25 this week. Window...
August 11 Construction Update for the Saint
The Saint: work begins on the 24th Floor next week. Saturday Work: There will be a crew on this Saturday, August 12, carrying out a variety of tasks. Outlook for the week of August 14 - August 19: Crews will begin working on forming, rebar installation and concrete...
August 4/23 Construction Update
The Saint: work on the 23rd Floor to be completed next week. Saturday Work: We do not expect significant work on site this holiday weekend, i.e. Saturday, August 5, though there may be some modest activity on the site. The site will be closed Monday, August 7 for the...
July 28 Construction Update
The Saint: work on the 23rd Floor set for the coming week.Saturday Work There will be a crew on site, Saturday, July 29, working on a variety of tasks throughout the site. Outlook for the week of July 31 - August 4 Crews will begin working on rebar installation,...
Upcomming Events
July
21
Community Information Session
Please join us on Tuesday, July 21 at 6:30 pm for an online information session reviewing the initial phases of construction of Minto’s The Saint at 89 Church Street.
Please click here for the details of the information session.