Concrete work continues on the parking levels as hoarding installation & servicing work continue. Saturday Work - October 16 There will be crews on site this Saturday, October 16. They will be conducting light work and general housekeeping tasks.  Look Ahead...

September Construction Report for The Saint.

September Construction Report for The Saint.

We are pleased to share the September Construction Report for The Saint, 89 Church Street: Please click here to download a PDF copy of the summary report. We have sent out a request to neighbouring building representatives, property managers and the St. Lawrence...

Construction Update for the Saint, October 8, 2021

Construction Update for the Saint, October 8, 2021

Overhead protection begins installation as site servicing work continues on Lombard St.No work on site this Saturday. Work will resume Tuesday, October 12. The City of Toronto approved contractors are continuing their work on Lombard Street. We are looking forward to...

Friday Update for the Saint, October 1, 2021

Friday Update for the Saint, October 1, 2021

Site servicing work moves to Lombard. Concrete work continues on the parking levels.UPDATE: There will be no work on Saturday, October 2. OJCR, the City of Toronto selected site services contractor has been setting up on Lombard Street today They will continue working...

Midweek Construction Update for the Saint, September 28, 2021

Midweek Construction Update for the Saint, September 28, 2021

Jersey barriers on Lombard St. to be moved Wednesday for site servicing work.Mid-Week UpdateWe expect the City of Toronto approved contractors to begin working on Lombard Street by Wednesday or Thursday this week. To prepare for this work, site crews will begin moving...

Construction Update for September 24, 2021

Construction Update for September 24, 2021

Concrete & site servicing work continues at the Saint. No work on site this Saturday. Work will resume Monday, September 27. The City of Toronto approved contractors are continuing their work is ongoing, occupying the western northbound lane of Church Street....

Construction Update for The Saint, September 17, 2021

Construction Update for The Saint, September 17, 2021

Hoarding installation delayed as site servicing work continues.No work on site this Saturday. Work will resume Monday, September 20. The City of Toronto approved contractors are continuing their work connecting the site to municipal services. Their work is taking...

Construction Update for the Saint, September 10, 2021

Construction Update for the Saint, September 10, 2021

Water connection work ends and hoarding installation begins this coming week. No work on site this Saturday. Work will resume Monday, September 13. Look Ahead for the week of September 14th.  The current City of Toronto Water connection work is expected to finish...

Construction Liaison Meeting – September 16, 2021

Construction Liaison Meeting – September 16, 2021

Please join us on Thursday, September 16, 2021 at 3:00 pm for the initial construction liaison meeting for Minto's The Saint, 89 Church Street. Please RSVP for the ZOOM Link by emailing us at contact@thesaintconstruction.info. The meeting will provide an overview of...

Construction Update for the Saint, September 3, 2021

Construction Update for the Saint, September 3, 2021

Look Ahead for the Saint for the Week of September 7, 2021. The site will be closed for the Labour Day holiday weekend. Work will resume on Tuesday, September 7. There will therefore be no work on Saturday. Look Ahead for the week of September 7th.  The site...

Upcomming Events

July

21

Community Information Session

Please join us on Tuesday, July 21 at 6:30 pm for an online information session reviewing the initial phases of construction of Minto’s The Saint at 89 Church Street.

Please click here for the details of the information session. 

Get In Touch