4th floor work remains the focus at The Saint.  Work at the Saint remains focused on the 4th floor, placing rebar (steel) into the forming structure, and then pouring Level 4 in sections. After each section is poured it will be finished to ensure it is level, smooth...

This week at the Saint. Construction Liaison Mtg Sept. 22.

This week at the Saint. Construction Liaison Mtg Sept. 22.

This week at the Saint: Decking. Forming. Concrete Pours. This week at the Saint work will be focused on finishing building out the decking for the 4th floor, placing rebar (steel) into the forming structure, and then pouring Level 4 in sections. After each section is...

Saturday Work and the outlook for the coming week at the Saint.

Saturday Work and the outlook for the coming week at the Saint.

Site work this Saturday, September 10, 2022. Construction highlights: There will be a crew on site tomorrow, Saturday, September 10, doing a a variety of housekeeping work and preparation work for the coming week. We do not expect that they will stay later than early...

The Saint, September 6 – 9, 2022

The Saint, September 6 – 9, 2022

Work on the 4th Level of the Saint progresses this week. Construction highlights: Vertical columns and walls are being formed and poured. Concrete slab work is ongoing in stages and sections: forming, rebar installation, concrete pouring and finishing. Deliveries will...

Construction Outlook, August 27 to September 2, 2022.

Construction Outlook, August 27 to September 2, 2022.

3rd Level slab floor set to be completed this coming week.  This coming week - construction highlights: We do not expect there to be work on-site this Saturday, August 27.  The 3rd Floor Slab remains unfinished. Work proress this past week was unfortunately slower...

Construction Outlook for August 20 – 26, 2022

Construction Outlook for August 20 – 26, 2022

Work on Level 4 will be the focus for the coming week.  This coming week - construction highlights: We have no confirmation of any work planned for Saturday, August 20 at the site, though there may be a small crew on-site doing prep work for the coming week, and/or...

Upcomming Events

July

21

Community Information Session

Please join us on Tuesday, July 21 at 6:30 pm for an online information session reviewing the initial phases of construction of Minto’s The Saint at 89 Church Street.

Please click here for the details of the information session. 

Get In Touch